Initial Aftercare

The design and construction team should appoint an aftercare team to represent it on post-handover aftercare duties for the initial period of aftercare to familiarize end-users with the general operation of the asset/facility and to provide training and technical support.

Design & Construction Team Responsibilities

The aftercare team should include a representative from the design and construction team and the representative(s) of the subcontractor(s) responsible for the building services engineering systems. They should:

Specific Actions:

  1. Record issues that have arisen and discuss remedial action with the owner’s representative.
  2. Provide input to early performance evaluation, comparing actual values with required outcomes and targets.
  3. Record comments about how specific products and elements perform and prepare reports on their performance.
  4. Identify changes made by the owner or operator that might have caused any impaired performance.
  5. Maintain records of technical guidance given to the operator or end-users.
  6. Report to the owner’s representative on how the operator is delivering the required performance outcomes.

Lead Appointed Party & Operator Responsibilities

The Lead Appointed Party, operator, operations team or facility manager should:

  1. Consider any operational costs that might have arisen that were not predicted and maintain records to inform lessons learned.
  2. Record input to any performance evaluation during this period.
  3. Maintain records of walkabouts on the part of the design and construction team (or aftercare team).
  4. Record informal end-user discussion; and maintain records of fine-tuning and any adjustments undertaken.